References – Petrochemical industry

COKE TAR REMOVAL PACKAGE FROM QUENCHWATER IN ETHYLENE PLANT

The project objective is to provide know how detail design and main equipment delivery of Coke Removal Unit (CRU) for removing of coke from quenchwater in ethylene plant (EP) in the project J3 in Jamnagar, Rajasthan, India. CRU is a part of a newly built petrochemical plant in the Western part of India located on the Indian Ocean coast.

 

DECOKING OF CRACKING FURNACES

Legislative emission limits of solid substances emitted to the ambient are constantly decreasing. Our company designed and installed technology for solid coke particles removal from the steam-air mixture during the furnace decoking including two inlet nozzles of different sizes and unique Coke Separation Chamber. Guaranteed emission rate is 20 mg/Nm3.

 

COKE REMOVAL FROM QUENCH OIL SYSTEM IN ETHYLENE PLANT

Design and procurement of a filtration unit for the quench oil loop. The filtration unit removes solid coke particles without any necessity for shutdown of the ethylene plant (EP), with no negative impact to the environment and to health and safety.

 

COKE REMOVAL FROM QUENCH OIL SYSTEM IN ETHYLENE PLANTS

Design and procurement of a filtration unit for the quench oil loop. The filtration unit removes solid coke particles without any necessity for shut down of the ethylene plant (EP). This system of filtration is the unique process, especially with respect to discharge of dry coke from the filters, with no negative impact to the environment and to health and safety. The process is designed and owned by Intecha.

 

REPLACEMENT OF COOLING COMPRESSORS

Replacement of cooling compressors K300 A/B/C by a pair of new cooling units, each of power rating of 720 kW. The cooling unit consists of screw compressors, a high pressure collector of the cooling fluid, air condensers and evaporators.

 

COKE REMOVAL FROM QUENCH OIL SYSTEM IN ETHYLENE PLANTS

Design and procurement of a filtration unit for the quench oil loop. The filtration unit removes solid coke particles without any necessity for shut down of the ethylene plant (EP). This system of filtration is the unique process, especially with respect to discharge of dry coke from the filters, with no negative impact to the environment and to health and safety. The process is designed and owned by Intecha.

 

COKE REMOVAL FROM QUENCH OIL SYSTEM IN ETHYLENE PLANTS

Design and procurement of a filtration unit for the quench oil loop. The filtration unit removes solid coke particles without any necessity for shut down of the ethylene plant (EP). This system of filtration is the unique process, especially with respect to discharge of dry coke from the filters, with no negative impact to the environment and to health and safety. The process is designed and owned by Intecha.

 

QUENCH OIL COKE REMOVAL IMPROVEMENT

The existing unit did not reach the required efficiency, and it had a very negative impact on HSE. Consequently, the unit was reconstructed according to a study and a basic design prepared by Intecha. The objective was to install process which meets BAT requirements.

 

CHARGE GAS SYSTEM PRESSURE DROP DECREASING

The goal of this project was decreasing of a pyrolysis gas pressure drop in the line of the primary fractionator, the water wash column and the alkali wash column. Consequently, it was necessary to replace the existing trays for new random packing, respectively for the alkali wash column to replace even the existing trays in the upper part for new trays with a lower pressure drop and to ensure the existing flow rate and composition of pyrolysis gas.

 

BENZENE UNLOADING FROM RAIL TANK CARS

The objective of the contract featured construction of a new unloading station for benzene to use as feedstock from external sources and to increase the existing capacity of Ethylbenzene II production plant in the area of UNIPETROL RPA, s.r.o., steam cracker.