Intecha finalized the concept of the process with giving the consequent functional guarantee of the entire system.
Reconstruction included modification of the existing storage tanks, procurement of new pumps and piping connections in the scope of the mechanical part of the project. Intecha was also responsible for all the civil, electrical and instrumentation parts of the project.
Reconstruction of the unloading station featured reconstruction of the existing unloading station to comply with the legislation of environmental protection, to improve safety, and to increase options of its use simultaneously.
The principal objective of the project was to decrease the emissions of hydrocarbons from storage tanks and from the loading station of benzene, pyrolysis oil, fuel oil, gas oil and C9 fraction.
The project solved an unacceptable state of the unloading of chemicals for chemical treatment of water from rail tank cars and its storage.
Design and construction of a complete system of vapors collection from storage tanks, loading of tank trucks and rail tank cars including safety valves, and detonation flame arresters.