NEW FLARE SYSTEM

Execution Time from: 01/2003
to: 04/2004
Execution Stage
Lump Sum Turn Key
Client ČESKÁ RAFINÉRSKÁ, a.s.
 

Installation of new pressure safety valves, construction of new unit headers, reconstruction of the off-gas piping in the inlet and the outlet from pressure safety valves, and connecting of the new flare gas system to the flare in the refinery in Kralupy nad Vltavou.

The existing pressure safety valves were replaced by new ones. All the other existing pressure safety valves and shut-off valves were overhauled. All the new and overhauled valves were equipped with Interlock locking device. Flow measurement of the flare gas flow was installed in the flare system.

Intecha disassembled 115 t of piping, valves and steel structure in total, and supplied and assembled 85 t of steel structure, 155 t of piping, 171 pcs of pressure safety valves, 348 pcs of valves and 322 locking devices.

Most of the assembly and disassembly was carried out during a shutdown of the refinery in 27 days.