COKE AND TAR REMOVAL PACKAGE (CTRP) FROM QUENCH WATER IN ETHYLENE PLANT (EP)

The scope was design and procurement of a Coke and Tar Removal Package (CTRP) from the quench water loop at the ethylene plant. The CTRP removed coke and tar without any necessity for shutdown of the quench water loop, with no negative impact to the environment and to health and safety.

 

TANK MODIFICATION

The aim of this project was to increase the butadiene storage capacity and to build a new line for the butadiene transport from the Liquefied Gas Storage Facility to the Chemical Production Area (CHPA).

 

BUTADIENE DISTILLATION

The new Butadiene Distillation unit removes the inlet butadiene moisture by azeotropic distillation before feeding it to other production units.

 

COKE REMOVAL FROM QUENCH OIL SYSTEM IN ETHYLENE PLANT

Design and procurement of a Coke Removal Unit (CRU) for the quench oil loop at the ethylene plant. The CRU removes solid coke particles without any necessity for shutdown of the ethylene plant (EP), with no negative impact to the environment and to health and safety.

 

A NEW LPG FEED LINE

A new LPG feed line is situated at an ethylene plant in UNIPETROL RPA, s.r.o. area.

 

TANK RECONNECTION

This project was carried out in the storage of feed liquids for cracking furnaces at the ethylene plant in UNIPETROL RPA, s r.o. area.

 

COKE REMOVAL FROM QUENCH OIL SYSTEM IN ETHYLENE PLANT

Design and procurement of a Coke Removal Unit (CRU) for the quench oil loop at the ethylene plant.

 

ZC9 PRODUCTION INCREASE

The purpose for the execution of the investment project "Increase in ZC9 Production" is to increase the C9 + fraction production on the ethylene unit by installing new reactors for dimeration of unsaturated C5 and C6 hydrocarbons.

 

DECOKING CYCLONE PACKAGED UNITS

Intecha designed and delivered two packaged units of highly efficient coke and steam-air mixture cyclone separators for Indorama Venture Olefins LLC ethylene cracker located in Lake Charles, Louisiana, USA.

 

FLARE RECONTRUCTION

The aim of this project was a off gas combustion quality (ecology) improvement, reliability enhancement and prolongation of the flare system operation cycles in SYNTHOS Kralupy a.s.